MASTER DRAINAGE STUDY (PHASE 2)
UPDATE (05/17/2023) -
• Concerning the feedback from the first public meeting, the citizen input on the display board was primarily along E. 91st St., N. Forest St., Wilmott Channel north of W. “G” St., W. “E” St. and the northern end of Juniper St.
• Delineation of the drainage areas for the portion of the drainage area to the east of the Wilmott Creek channel is in progress and will continue to the west side of Wilmott Channel now that all LIDAR data is available.
• Sub-basin areas are being identified, soil data has been downloaded from the NRCS web site, and an initial HEC HMS model schematic and input data for the model is being finalized.
• The model is expected to be completed by May 15.
UPDATE (04/01/2023) - The first public meeting is set for 04/25/2023 at 6pm at City Hall.
DRAINAGE AND STORM SEWER MASTER PLAN (PHASE 1)
UPDATE 10/05/2022 - Second Public Meeting held on 9/29/2022 and was attended by nine residents. The consultant will provide final report to staff soon.
UPDATE 10/22/2021- First Public Meeting held on October 21 attended by 13 residents.
EAST "F" STREET STORM SEWER EXTENSION PROJECT
UPDATE 10/05/2022 - The Real Estate License Agreement will be on the Jenks Public School Board October 10th Agenda for approval.
aRKANSAS RIVERBANK STABILIZATION DESIGN
UPDATE 10/05/2022 - Staff has received and is reviewing a proposal from the design consultant to create a detailed design for a barrier wall along the bank of Arkansas River between the Main Street and Creek Turnpike bridges.